Semi inground pool installation

Semi inground pool installation

It takes approximately 3 days to install a semi inground pool. Please note that bad weather may cause delays.

One installation day :

  • Location of the pool and passage of machinery

  • Excavation and disposal of land

  • Digging

  • Installation on concrete block

  • Installing the French drain (auxiliary drain)

  • Concrete Base on the braces (for models oval)

  • Bottom drain in the cement

  • Sand bottom

  • Backfill with sand to the contour

  • The installation of the filtration system and various accessories (heat pump, water heater, running, scale, etc.)

Expect extra charges for :

  • Level differences of more than 6"

  • Saucer depth of over 6"

  • Removing earth and turf from your yard

  • Removing stumps

  • Installing a deck

  • Installing a solar blanket roller

  • Installing a water-heater with a bypass

  • Connecting a gas line for a propane or natural gas water-heater

  • Licensed electrician for electrical hook-up

  • Removing sod

  • Leveling the ground and digging the saucer (4 to 6 inches)

  • Light(s) installation